Maintenance and resurfacing work

Published: 23 September 2021

Maintenance and resurfacing work to the entirety of the roundabout on Lyne Road with the junction of Wilsden Way and Thorne Close in Kidlington.

Works are programmed to start on Friday 15th October 2021 and are expected to last for two nights, subject to any bad weather conditions or unforeseen circumstances during construction.

Works will include ironwork adjustments and the resurfacing of the existing carriageway, following which all existing and legal road markings and lines will be reinstated.

Traffic Management

In order to keep traffic disruption to a minimum, the works will be carried out under two overnight full road closures from 2000-0600hrs, being on Friday and Monday, on either side of the weekend. Lyne Road and the Wilsden Way roundabout will be fully reopened outside of these hours. A fully signed local diversion route will be put in place for the scheme duration.

Works have been programmed to complete the resurfacing in two phases, which will allow residential access to both Thorne Close and Wilsden Way to be maintained throughout. The northern half of the roundabout will be closed on Friday, with access via Grovelands and Lyne Road South. The southern half of the roundabout will be closed on Monday night, with access via Lyne Road north and via the A4260 Banbury Road. We apologise unreservedly for any inconvenience this may cause.

Surfacing operations are moving operations so the highest levels of noise will only be experienced by individual frontages for short periods. The nosiest operation, the planing will be completed by 2300hrs on each night.

Coronavirus (COVID-19) – Compliance with Government Advice
Where road and transport services are concerned, the government has stated that any work that can be done safely and within Public Health England guidance can continue.

We are continuing to carry out essential repairs to the network to ensure that roads remain operational, safe, and serviceable.

An assessment of each location has been completed to ensure that the works can be undertaken in accordance with specially enhanced safe working practices. All our contractors are ensuring that working practices relevant to government guidance can be adhered to.

If you see anyone working on the roads, they are performing a vital service. Please observe social distancing rules.

Keeping You Informed

If you think the works will cause you particular problems with access or deliveries or require further information, then please telephone, or email the appropriate contact below and we will be happy to answer any queries that you may have.

Office Contact
Please use in advance of the works regarding any issues raised in this letter Site Contact
Please use during the works
Scott White
Technical Officer
Highway Maintenance, Cherwell
Area Operations (North)
Oxfordshire County Council
0345 310 1111
Highway.Enquiries@Oxfordshire.gov.uk Stuart Bowler
Works Manager (Schemes)
Oxfordshire County Council
0345 310 1111
Highway.Enquiries@Oxfordshire.gov.uk


Finally, we wish to apologise in advance for any disruption or inconvenience that these works may cause. Our intention is to provide you with a better road surface as safely and as quickly as possible.

Road works notice Oct 2021